Proven Engagements

Three projects, three recoveries.

From our founders' real-world delivery history. Client names and sensitive details are withheld; the situations, methodologies, and outcomes are 100% authentic.

Estimation · Project Recovery

Signed for 2,500 hours. Needed 11,000.

Situation
We joined in sprint 3. The engineering team was still struggling to finalize sprint 1 tasks, while the client was introducing detailed scope changes mid-sprint. The contract had been signed as a fixed commitment of 2,500 to 3,000 hours.
What We Found
The initial sales estimate had been prepared in haste without deep requirement analysis. Re-estimating alongside the technical team revealed the realistic backlog required no less than 11,000 hours.
What We Did
Management was reluctant to confess the disparity to the client. We built the business case for absolute transparency and presented three clear paths forward:
  1. Re-calibrate the entire scope and re-plan with adjusted commercials
  2. Ruthlessly trim scope to preserve the committed hard launch date
  3. Prioritize: ship core MVP features by the deadline, followed by short, continuous weekly release increments
Outcome
The client selected Option 3. A robust, functional MVP shipped on time for their commercial product launch. Subsequent features rolled out predictably every 7 to 8 days until the complete engagement was delivered.
“A problem presented with actionable options is no longer a crisis — it is a plan.”
Estimation Recovery Case Study
Team Structure · Agile Governance

Five teams, one feature, no owner.

Situation
A large-scale project was organized strictly by technical layers: Backend, Frontend, UI/UX, Business Analysis, and QA.
What We Found
Every user story cut horizontally across every layer. Whenever a release slipped, it triggered cross-team friction and blame loops. Not a single person was accountable for a feature functioning end-to-end.
What We Did
We dissolved horizontal component silos and restructured the engineering organization into vertical, cross-functional feature squads. Each squad owned their module from user story refinement to production deployment.
Outcome
Friction plummeted. Velocity increased by over 40%. Full ownership rested with each dedicated squad, enabling internal problem solving rather than inter-departmental finger-pointing.
“When every team owns a layer, nobody owns the feature.”
Agile Team Structure Case Study
Requirements Alignment · Recovery

“This is not what I asked for.”

Situation
We were brought in to salvage a troubled initiative that had spent 18 months attempting to deliver its initial build. Upon demo, the client rejected the release outright: “This is not what I asked for. You misunderstood our business.”
What We Found
Critical thinking regarding requirements was taking place at delivery time rather than at discovery time. Developers were forced to make assumptions in isolation.
What We Did
We instituted rigorous discovery and verification rituals. We secured stakeholder commitment to an explicit Definition of Ready, shifting the hard debates into interactive acceptance criteria sessions before a single line of code was written.
Outcome
The relationship was repaired. The rewritten milestone was accepted on the first review, and the project proceeded to a successful production rollout.
“Arguments are cheapest during requirements discovery and most expensive at release deployment.”
Requirements Recovery Case Study

Recognize one of these delivery patterns?

A two-week Project Health Check diagnoses which anti-pattern your team is facing and gives you a concrete recovery roadmap.

See the Health Check